NASA will equip Crew-12 and Artemis II astronauts with smartphones for the first time, as the agency advances prelaunch ...
NASA Artemis 2 mission after encountering hydrogen leaks during a fueling test of the Space Launch System. The Space Launch ...
NASA early Tuesday announced it was pushing the launch date of its Artemis II mission to March, after engineers encountered a ...
Despite challenges, technicians filled all tanks, dispatched a five-person team for Orion closeout, and safely drained the rocket.
This is starting to sound oddly familiar NASA has concluded a Wet Dress Rehearsal (WDR) for Artemis II, but recurring liquid hydrogen leaks forced the test to be halted short of completion, prompting ...
NASA has delayed its Artemis 2 moon launch until March at the earliest, after encountering some issues during a key prelaunch ...
According to Space.com, there are five potential launch dates available in March for Artemis 2, which will lift off from NASA ...
The convergence of the Artemis II and Crew-12 launch schedules adds another layer of importance to Monday’s countdown test at Kennedy Space Center. For the first time since the 1960s, NASA has ...
During the test, teams loaded cryogenic propellant into the tanks of the Space Launch System (SLS), sent personnel to the launch pad to complete ...
The wet dress rehearsal for NASA’s Artemis II concluded early Tuesday morning. The SLS (Space Launch System) tanks were ...
NASA defended preparations for Artemis 2 after a fueling test had hydrogen leaks like those that bedeviled Artemis 1 more ...
During a press conference on Tuesday afternoon, NASA officials said that due to a liquid hydrogen leak and other issues, they ...